EAC Calculator: Calculate Estimate at Completion (+ Excel Guide)


Estimate at Completion (EAC) Calculator

Forecast your project’s final cost based on current performance data.


The total original budget planned for the project. (Currency: $)


The budgeted cost of work scheduled to be completed as of today. (Currency: $)


The value of the work actually completed to date. (Currency: $)


The total cost actually incurred to complete the work so far. (Currency: $)


Primary EAC (Based on Current CPI)
$0.00

Cost Performance Index (CPI)
0.00

Schedule Performance Index (SPI)
0.00

Cost Variance (CV)
$0.00

Schedule Variance (SV)
$0.00

Estimate to Complete (ETC)
$0.00

Variance at Completion (VAC)
$0.00

Budget vs. Forecast Chart

A visual comparison of original budget against actual and forecasted costs.

What is Estimate at Completion (EAC)?

Estimate at Completion (EAC) is a critical forecasting metric in project management used to predict the total cost of a project at its conclusion. Unlike the initial Budget at Completion (BAC), which is a static figure set during the planning phase, EAC is a dynamic calculation that adjusts based on the project’s actual performance to date. By incorporating real-world data like actual costs and work progress, EAC provides project managers with a realistic financial forecast, enabling them to make informed decisions to keep the project on track and manage stakeholder expectations.

EAC Formulas and Explanation

There isn’t a single formula for EAC; the correct one to use depends on the nature of the project’s variances. If cost variances are expected to continue, you use a performance-based formula. If they are atypical, you might use a different one. The most common formulas are essential for anyone looking to calculate EAC using Excel or any project management tool.

Common Formulas

  • EAC = BAC / CPI: This is the most used formula. It assumes the cost performance to date (CPI) will continue for the remainder of the project.
  • EAC = AC + (BAC – EV): This formula is used when current variances are considered atypical, and you expect the remaining work to be completed at the originally planned rate.
  • EAC = AC + [(BAC – EV) / (CPI * SPI)]: This formula is used when both cost and schedule performance are expected to impact the rest of the project.
Description of Variables for EAC Calculation
Variable Meaning Unit Typical Range
BAC Budget at Completion Currency ($) Positive Value
PV Planned Value Currency ($) Positive Value
EV Earned Value Currency ($) Positive Value
AC Actual Cost Currency ($) Positive Value
CPI Cost Performance Index (EV / AC) Ratio >1 (Under Budget), <1 (Over Budget)
SPI Schedule Performance Index (EV / PV) Ratio >1 (Ahead of Schedule), <1 (Behind Schedule)

Practical Examples

Example 1: Software Development Project

A team is developing a new mobile app with an initial budget (BAC) of $150,000. At the halfway point, they have spent (AC) $90,000, but the value of work completed (EV) is only $70,000. The planned value (PV) for this point was $75,000.

  • Inputs: BAC = $150,000, AC = $90,000, EV = $70,000, PV = $75,000
  • Calculation: CPI = $70,000 / $90,000 = 0.78
  • Result (EAC): EAC = $150,000 / 0.78 = $192,308. The project is forecasted to be over budget.

Example 2: Construction Project

A small office building is being constructed with a BAC of $2,000,000. After three months, the AC is $550,000, and the EV is $600,000. The variance is due to a one-time favorable materials contract that won’t be repeated. The rest of the project is expected to proceed as planned.

  • Inputs: BAC = $2,000,000, AC = $550,000, EV = $600,000
  • Calculation: Using EAC = AC + (BAC – EV) because the variance is atypical.
  • Result (EAC): EAC = $550,000 + ($2,000,000 – $600,000) = $1,950,000. The project is now forecasted to come in slightly under budget.

How to Use This EAC Calculator

This calculator helps you easily determine your project’s financial forecast. Follow these steps:

  1. Enter Budget at Completion (BAC): Input the total approved budget for your project.
  2. Enter Planned Value (PV): Input the budgeted cost for the work that was scheduled to be completed by the measurement date.
  3. Enter Earned Value (EV): Input the value of the work that has actually been completed.
  4. Enter Actual Cost (AC): Input the total money spent to date.
  5. Review the Results: The calculator automatically provides the EAC based on the most common formula (BAC / CPI), along with key performance indicators like CPI, SPI, and cost/schedule variances. The chart visualizes how your forecast compares to the original budget.

How to Calculate EAC Using Excel

Calculating EAC in Excel is straightforward. You can set up a simple spreadsheet to track your project’s financial health.

  1. Set Up Your Columns: Create columns for BAC, PV, EV, and AC.
  2. Enter Your Data: Populate these columns with your project’s data.
  3. Create Formula for CPI: In a new cell, calculate the Cost Performance Index with the formula =EV_cell / AC_cell (e.g., =C2/D2).
  4. Calculate EAC: In another cell, use the formula =BAC_cell / CPI_cell to find the EAC.
  5. Expand with Other Formulas: You can add rows to calculate the other EAC variations, as well as metrics like CV, SV, and VAC to create a comprehensive dashboard.

Key Factors That Affect EAC

The accuracy of your EAC is influenced by several factors that project managers must monitor closely.

  • Scope Creep: Uncontrolled changes or additions to the project scope are a primary cause of budget overruns.
  • Resource Costs: Unexpected changes in labor rates, material prices, or equipment rental fees can significantly impact the actual cost (AC).
  • Risk Events: The occurrence of unplanned risks can lead to additional work and expenses, throwing off the original forecast.
  • Inaccurate Initial Estimates: If the original BAC was poorly estimated, the EAC will be correcting for those initial errors from the start.
  • Team Performance: The efficiency and productivity of the project team directly influence the relationship between EV and AC (the CPI).
  • Data Accuracy: EAC is only as reliable as the input data. Inaccurate or delayed reporting of AC or EV will lead to a misleading forecast.

Frequently Asked Questions (FAQ)

1. What’s the difference between EAC and BAC?
BAC (Budget at Completion) is the original, approved budget for the entire project, set during the planning phase. EAC (Estimate at Completion) is a forecast of the final cost, calculated during project execution, based on actual performance.
2. What is a “good” CPI value?
A CPI greater than 1.0 indicates you are under budget (good performance). A CPI less than 1.0 means you are over budget. A CPI of exactly 1.0 means you are right on budget.
3. How often should I calculate EAC?
EAC should be calculated regularly, typically at the same frequency as your project status reporting (e.g., weekly, bi-weekly, or monthly). Frequent calculation helps in early detection of potential issues.
4. Which EAC formula is the best to use?
It depends on your project’s situation. If you believe the current cost performance is a good predictor of future performance, use EAC = BAC / CPI. If the current variances were a one-time issue, use EAC = AC + (BAC – EV).
5. Can my EAC be lower than my BAC?
Yes. If your CPI is greater than 1.0 (meaning you are performing more efficiently than planned), your EAC will be lower than your BAC, indicating a potential cost saving.
6. What is ETC (Estimate to Complete)?
ETC is the forecasted cost to finish the remaining project work. The simplest EAC formula is actually EAC = AC + ETC. The various EAC formulas are essentially different ways of calculating the ETC based on past performance.
7. How does SPI (Schedule Performance Index) relate to EAC?
While CPI directly impacts the cost forecast, SPI indicates schedule efficiency. In some EAC formulas, a low SPI can increase the forecasted cost, as schedule delays often have cost implications (e.g., extended labor, equipment rental).
8. What do I do if my EAC is much higher than my BAC?
If your EAC shows a significant budget overrun, you must take corrective action. This could involve finding ways to reduce costs, descoping certain project requirements, or formally requesting additional budget from stakeholders with a clear explanation of the variances.

Related Tools and Internal Resources

To further understand project financials and performance, explore these related concepts and tools:

© 2026 Your Company. All Rights Reserved. This calculator is for informational purposes only.



Leave a Reply

Your email address will not be published. Required fields are marked *